  • Bamfield Main Road Update – December 12, 2022

    Bamfield Main Road Update – December 12, 2022

    For the period of December 12 – December 16, 2022  

    Please note that changes to the Bamfield Main Road detour route are now in effect. Drivers can expect to be detoured from Bamfield Main Road between 36 km and 49 km. 

    2022-12-12-new-detour-map- Bamfield Main Road
    Bamfield Main Road Detour Map effective December 12, 2022

    There will be no access to Bamfield Main Road from 39km to 49 km. All traffic, both industrial and public, will be required to use the detour. Drivers should slow down and be prepared for industrial traffic throughout the detour area. 

    Drivers can expect single-lane traffic and delays at approximately three locations between Port Alberni and Bamfield, each with a minimum of 15 minutes delay. Both traffic control persons at stops and/or automated flagging devices with pilot cars will be utilized. 

    All  travellers are required to use the detour, and those who attempt to bypass the detour will be turned back.  

    Please slow down and expect additional delays due to the changing weather conditions. Winter driving conditions should be expected, and all public drivers should check weather conditions before travelling and be prepared. Please avoid driving during extreme weather conditions.  

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment, flaggers, and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.  

    Crews will continue to work on ditching, culvert replacement, and beam barriers. 

  • Bamfield Main Road Detour Update

    Bamfield Main Road Detour Update

    Bamfield Main Resurfacing Project Header

    The detour route has changed. Please continue to use the detour marked from 36 km – 49 km.

    All traffic, both industrial and public, will be required to use the detour. Drivers should slow down and be prepared for industrial traffic throughout the detour area. 

    Drivers can expect single-lane traffic and delays at approximately three locations between Port Alberni and Bamfield, each with a minimum of 15 minutes delay. Both traffic control persons at stops and/or automated flagging devices with pilot cars will be utilized. 

    All  travellers are required to use the detour, and those who attempt to bypass the detour will be turned back.  

    Please slow down and expect additional delays due to the changing weather conditions. Winter driving conditions should be expected, and all public drivers should check weather conditions before travelling and be prepared. Please avoid driving during extreme weather conditions.  

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment, flaggers, and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.  

    Crews will continue to work on ditching, culvert replacement,  and beam barriers. 

  • Fall 2022 Community Update Video

    Huu-ay-aht First Nations is proud to release our Fall 2022 Community Update Video showcasing Huu-ay-aht First Nations milestones of 2022. The video highlights the Kiix̣in National Historic Site Plaque Reveal, the Bamfield Main Road Surfacing Project, and the continued growth of Upper Anacla. 

    On September 20, 2022, Huu-ay-aht and Parks Canada celebrated the installation of a plaque at the Kiix̣in Village and Fortress. Haw̓iiḥ Councillor Jeff Cook (Yał luu a) and Chief Councillor Robert J. Dennis Sr. joined Kiix̣in tour guide and knowledge holder Wišqii as he opened the ceremony. 

    Through a partnership with Parks Canada, Huu-ay-aht First Nations will continue to share their culture and history with visitors with guided tours of the only known remaining First Nations Village on the west coast of southern B.C. through Kiix̣in Tours.

    What is different about this is Huu-ay-aht is starting to design it’s economy. What do we need to do to make a strong economy? 

    Chief Councillor Robert J. Dennis Sr. 

    The Bamfield Main Road Surfacing Project continues to progress with crush, resurfacing, and grading. The project is expected to be completed by April 2022. The safety of  travellers on Bamfield Main Road from Bamfield to Port Alberni has been important to Huu-ay-aht First Nations for generations and surfacing the road will help bring Huu-ay-aht community members home.  

    Uncle Spencer always said that the work we had done for the designation was something that his father, our grandpa, wanted to do but he didn’t know how to put it into words.   

    Stella Peters, citizen, Kiix̣in tour guide

    Charlie Clappis shares how the community of Anacla has grown over the last five years, plans for the Huu-ay-aht First Nations Cultural Centre and considerations for the development of Anacla in the future.

  • Bamfield Main Road Update – December 5, 2022

    For the period of December 5 – December 11, 2022  

    There will be no access to Bamfield Main Road from 36km to 58 km. All traffic, both industrial and public, will be required to use the detour. Drivers should slow down and be prepared for industrial traffic throughout the detour area. 

    Drivers can expect single-lane traffic and delays at approximately three locations between Port Alberni and Bamfield, each with a minimum of 15 minutes delay. Both traffic control persons at stops and/or automated flagging devices with pilot cars will be utilized. 

    All  travellers are required to use the detour, and those who attempt to bypass the detour will be turned back.  

    Please slow down and expect additional delays due to the changing weather conditions. Winter driving conditions should be expected, and all public drivers should check weather conditions before travelling and be prepared. Please avoid driving during extreme weather conditions.  

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment, flaggers, and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.  

    Crews will continue to work on ditching, culvert replacement,  and beam barriers. 

  • Bamfield Main Road Update – November 28, 2022

    For the period of November 14 – December 4, 2022  

    The Bamfield Main Road detour remains in place from approximately 36 km to 58 km adding up to an extra hour of driving time for public drivers.

    Please slow down and expect additional delays due to the changing weather conditions. Winter driving conditions should be expected, and all public drivers should check weather conditions before travelling and be prepared. Please avoid driving during extreme weather conditions.

    Drivers can expect single-lane traffic and delays at approximately three locations between Port Alberni and Bamfield, each with a minimum of 15 minutes delay. Both traffic control persons at stops and/or automated flagging devices with pilot cars will be utilized.

    Only industrial traffic will have access through construction areas. All other travellers are required to use the detour, and those who attempt to bypass the detour will be turned back.

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.

    Crews will continue to work on culvert replacement, borrowing, grid placement, ditching, and beam barriers.

  • Bamfield Main Road Update – November 21, 2022

    For the period of November 21 – 27, 2022   

    The Bamfield Main Road detour remains in place from approximately 36 km to 58 km, adding up to an extra hour of driving time for public drivers.  

    Only industrial traffic will have access through construction areas. All other travellers must use the detour, and those who attempt to bypass the detour will be turned back. 

    Drivers can expect single-lane traffic and delays at approximately three locations between Port Alberni and Bamfield, each with a minimum delay of 15 minutes. Expect traffic control persons at stops and/or automated flagging devices with pilot vehicles.   

    Industrial traffic may be utilizing the public access detour, and drivers should use extra caution, with an expectation of increased industrial traffic. Please slow down, as traffic control personnel may be found throughout the public access detour.  

    Please expect additional delays due to the changing weather conditions and the movement of construction materials and equipment.   

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.  

    Crews will continue to work on ditching, culvert replacement, borrowing, grid placement, and beam barriers.

  • Bamfield Main Road Update – November 14, 2022

    For the period of November 14 – 20, 2022   

    The Bamfield Main Road detour remains in place from approximately 36 km to 58 km, adding up to an extra hour of driving time for public drivers.  

    Drivers can expect single-lane traffic and delays at approximately four locations between Port Alberni and Bamfield, each with a minimum of 15 minutes delay. Expect traffic control persons at stops and/or automated flagging devices with pilot vehicles.   

    Only industrial traffic will have access through construction areas. All other travellers must use the detour, and those who attempt to bypass the detour will be turned back.    

    Please slow down, as traffic control personnel can be found throughout the public access detour.  

    Please expect additional delays due to the changing weather conditions and the movement of construction materials and equipment.   

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.   

    Crews will continue to work on culvert replacement, borrowing, grid placement, ditching, beam barriers, and sign installations.  

  • Bamfield Main Road Update – November 7, 2022

    For the period of November 7 – 13, 2022 the Bamfield Main Road detour remains in place from approximately 36 km to 58 km. Drivers can expect single-lane traffic and delays of up to 15 minutes at approximately three automated flag systems with pilot cars placed on both sides of the detour.  

    Only industrial traffic will have access through construction areas. All other travellers are required to use the detour, and those who attempt to bypass the detour will be turned back.  

    All traffic can expect new delays of 15 – 30 minutes outside of the detour as ditching is now underway at 34 km. New delays may be experienced at bridges as well. 

    Please expect extra additional delays due to the changing weather conditions and the movement of construction materials and equipment. 

    Speed should not exceed 60 km per hour, and drivers are required to slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour. 

    Crews will continue to work on culvert replacement, borrowing, grid placement, ditching, and sign installations. 

  • Bamfield Main Road Update – October 27, 2022

    Bamfield Main Road Update – October 27, 2022

    The Bamfield Road Surfacing Project experienced it’s first heavy rainfall and we are happy to let you know that the work being done is preventing sediment from going into the River.

    What did the crew do to prepare for this?

    Along the bank of the river and lake, where the road is higher than the body of water, they line it with riprap. Riprap are large rocks (a foot or bigger). They are placed tightly together along the banks so when the rain is hitting the road and draining towards the river or lake, the sediment gets filtered through the riprap. This works both ways as well. When lake and river waters rise from a lot of heavy rainfall, the riprap will prevent the road from getting washed away from these rising waters. This is an important feature to protect our wildlife and keep our drivers safe. Good job road crew!

    IMG_2021
    Riprap placed along Sarita River

    Ditch You Know?

    The new ditches have all been hydro-seeded or hand seeded and new growth has sprouted for many kilometres. While we wait for the grass to grow, rock check dams have been placed in the ditches to reduce the flow rate of water, which allows any sediment to settle out. The runoff is being monitored by the team and they are checking critical areas to ensure there is no impact to the waterways.

    IMG_1886
    Rock check dam in the ditch
    IMG_1893
    Rock check dam slowing down the flow of water
  • Bamfield Main Project Update

    Bamfield Main Project Update

    Bamfield Main Resurfacing Project Header

    Some of the reasons why you should not drive through the construction zone:

    IMG_1904
    The crew is busy repairing many culverts for proper drainage. This creates very large holes in the road that would be hard to see, especially in the dark.
    IMG_1839
    Unexpected traffic puts the road crew at risk. They work around noisy equipment, may have hearing protection on, and will not hear traffic coming.
    IMG_1921
    Equipment could potentially be left on the road so crew members can pick up where they left off the next day. These could be hard to see at night as well.
    IMG_1878
    If you were to have an accident, get a flat tire, or your vehicle was to break down, you could potentially be stuck there for a very long time as no other traffic would be coming along.
    IMG_1945
    Vehicles driving through the construction site can also cause damage to the road setting progress back and making the road project take longer.