News Categories: Bamfield Main Road

  • Bamfield Main Road Update – October 18, 2022

    For the period of October 18 – 23, 2022, the Bamfield Main Road detour will be in place from approximately 36 km to 58 km. Drivers can expect single-lane traffic and waits at one or two automated flag systems with pilot cars, each with a delay of up to 15 minutes.

    Only industrial traffic will have access through construction areas. All other travellers are required to use the detour.

    Speed should not exceed 60 KM per hour, and drivers must slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.

    Crews will continue to work on culvert replacement, borrowing, grid placement,

    Please continue to obey posted speed limits and do not exceed 60 KM. Drivers should slow down around any new construction areas, construction crews, and equipment.

  • Bamfield Main Road Update – October 11, 2022

    For the period of October 11- 16th 2022, the Bamfield Main Road detour will be in place from approximately 36 km to 58 km. Drivers can expect single-lane traffic and delays of up to 15 minutes at two automated flag systems with pilot cars (approximately 68 km and 63.5 km.)

    Only industrial traffic will have access through construction areas. All other travellers are required to use the detour.

    Speed should not exceed 60 KM per hour, and drivers are required to slow down when construction equipment and crews are on the road. The RCMP will be monitoring for safe driving throughout the project and detour.

    Crews will continue to work on culvert replacement, borrowing, grid placement, and ditching.

    Please continue to obey posted speed limits not exceeding 60 KM and slow down around any new construction areas and construction crews and equipment.

  • Bamfield Main Road Update – October 3, 2022

    For the period of October 3 – 7, 2022 the full detour will be in effect from 36 KM and 58 KM on Bamfield Road. Starting Wednesday, October 5, drivers should expect some single alternating traffic. Crews will continue to work on culvert replacement, borrowing, grid placement, and ditching.

    Only industrial traffic will have access through construction areas. All other travelers should be using the detour.

    Please continue to obey posted speed limits not exceeding 60 KM and slow down around any new construction areas and construction crews and equipment.

    Drivers are required to wait for pilot vehicles at any automated flag equipment when lights are red. Expected wait for pilot vehicles is not to exceed 20 minutes.

  • Urgent Bamfield Main Road Project Notice

    Urgent Bamfield Main Road Project Notice

    For Visitors and Citizens using Bamfield Road

    Do not drive around the automated flags at the construction site. The construction crew is working to minimize the delays, which are typically no more than 15 minutes. Everyone using the road must wait for the pilot vehicle to guide them through this section of construction.

    Vehicles that have been driving around the flags are putting themselves and workers in danger. The flags are a vital part of the project’s safety planning. Cameras are in place to monitor traffic in this area and will be throughout the entire Bamfield Main Road Resurfacing Project. The RCMP are now assisting in enforcing the road safety rules and any criminal activities that take place. These issues could possibly delay the opening of the road and may require more strict actions for the traffic. ƛ̓eekoo (Thank you) for your cooperation.

    NOTICE
  • Bamfield Main Road Update – September 26, 2022

    Construction continues on the Bamfield Main Project. The full detour remains in effect both for the public and residents. RCMP monitoring of the road is underway to ensure safe driving practices are being adhered to. Access points to Poett Nook and Sarita are being maintained.

    All industrial traffic will have access through construction areas with limited delays. The 60 KM speed limit remains in effect on the detour 24 hours a day seven days a week. Crews will continue working on culverts, borrow fill, rip rap, bridge building, signage, and crush placement. Watch for flaggers and construction crew and reduce speed in construction areas.

    Visitors, citizens, and Huu-ay-aht staff using the road are asked to expect delays and to obey road signs and flaggers. The detour is in place 24 hours a day regardless of construction work taking place. Please visit: https://huuayaht.org/bamfield-road-information for the latest public updates.

  • Bamfield Main Road Detour

    Bamfield Main Road Detour

    The detour from 35.86 to 67.84 KM will be in effect until the beginning of October. Please drive with caution and give yourself more time for travel.

    For questions about the Bamfield Main Road Surfacing Project, please contact communications@huuayaht.org.

    Bamfield-Main-Detour-Update
  • The Association of Wetland Stewards for Clayoquot & Barkley Sound and Huu-ay-aht Work Together to Protect the Toad Habitation

    The Association of Wetland Stewards for Clayoquot & Barkley Sound and Huu-ay-aht Work Together to Protect the Toad Habitation

    Since 2018, The Association of Wetland Stewards for Clayoquot & Barkley Sound and Huu-ay-aht First Nations have been working together to protect the toad population at Frederick Lake. Over the years, they have taken steps together to protect important toad habitat close to the lake. When Wetland Stewards heard about the Bamfield Main Road Resurfacing Project, they saw another opportunity in protecting connections between habitats, the lake, and surrounding forests by installing wildlife tunnels.

    Their first project was installing educational signs and temporary barriers to protect toadlets from being trampled on the north shore of the lake where they emerge in high numbers. Toadlets are baby toads that have just transformed from tadpoles. They come ashore, spend several weeks close to the water, then disperse into the surrounding forest. It’s easy to trample them unintentionally because they are so tiny and difficult to see.

    Wetland Stewards worked with Huu-ay-aht Lands and Natural Resources staff to design the educational signs for the site. Edward R. Johnson designed a welcoming sign for those visiting Huu-ay-aht traditional territory with encouragement to follow Huu-ay-aht sacred principles while visiting the site.  The sacred principles are ʔiisaak (greater respect), ʔuuʔałuk (taking care of), Hišuk ma c̕awak (everything is one).

    Edwards-toad-sign

    In 2021, Wetland Stewards and Huu-ay-aht First Nations took further steps together to protect the toadlets by installing permanent barriers, placing logs, and planting native vegetation. This took place at the end of the road that provides access to the water pump that supplies water to Poett Nook Marina and Sarita log sort.  Huu-ay-aht First Nations provided a bobcat and operator (Don Prevost) and labourer (Alec Frank) for several days to complete this task. To further support the project, Huu-ay-aht Forestry LP provided concrete blocks, rocks, and gravel for the barriers, Stan Coleman (Forestry Advisor, Rocky Point Forest) provided time to help coordinate the delivery of those materials, and the BC Ministry of Transportation and Infrastructure provided the toadlet barrier material.

    Planning for the toad tunnels under the Bamfield Main Forest Service Road began in spring of 2021. Toadlets get killed crossing the roads that surround Frederick Lake when they disperse into the surrounding forest. Adult toads get killed crossing the roads when they migrate back and forth to breed at the lake each spring.

    To determine where toadlets and toads are in danger, former Huu-ay-aht staff, Katie Turner, conducted surveys to document locations where toads and other amphibians cross the Bamfield Main. Participants in these surveys were The Wetland Stewards trained technicians, the Huu-ay-aht Watershed Renewal Program staff, Huu-ay-aht Lands and Resources Department staff, and several volunteers from the community of Anacla and Bamfield.

    toad-workers

    The surveys happened during the migration periods in spring 2021 and 2022 and fall 2021. They spent 14 rainy nights doing these surveys per period for a total of 42 nights. Crews walked 2 km on the Bamfield Main Forest Service Road starting at least one hour after sunset on those rainy nights. Each time they found an amphibian, they recorded the species, age, class, and sex.  They used a GPS app on their phone to record the location. They also did surveys to find the main shoreline areas around the lake where adults laid eggs and where tadpoles congregated and transformed into toadlets. They did daytime surveys in the summer to find where toadlets crossed the road. They put cameras on the drainage channels at three existing culverts to capture photographs of the toadlets moving toward the road and through one of the existing culverts. They synthesized their findings with maps to pinpoint the best places for installing tunnels under the road. The Habitat Conservation Trust Foundation provided partial funding to cover some of the Watershed Renewal Program technicians’ time and mileage on the surveys. Most of the cost was covered by Huu-ay-aht First Nations.

    Wetland Stewards worked with engineers at Parsons Corporation to design toad tunnels for the road. They investigated existing drainage culverts to see whether they had the potential to serve as passageways for toadlets.  They also looked at provincial guidelines for tunnel structures that would work for adult toads. Using the location data collected on the night surveys, they chose the most concentrated locations for adult crossings as places to put two concrete box culverts. Three existing drainage culverts that occur in peak areas for toadlet dispersal were highlighted for repairs so that they can function for wildlife passages when not carrying water. This is usually the case when the toadlets are moving away from the lake in August and September; the driest time of the year.

    toad-tunnel

    In 2021-2022, Huu-ay-aht contributed approximately $10,000 for road surveys, shoreline surveys, barrier installation, and habitat restoration work.

    In 2022-2023, it is estimated that Huu-ay-aht will contribute a similar amount for surveys, building fencing to the new culverts, and monitoring movements of toads through the culverts (approximately $10,000 to the project).  Huu-ay-aht will also make a substantial investment through the funding for resurfacing the road.

    The Association of Wetlands Stewards for Clayoquot and Barkley Sounds welcomes anyone who is keen to come out and volunteer on fence building. Please send an email to wetlandstewards@gmail.com to let them know if you’d be available in August.

  • Detour on the Bamfield Main Road starts Monday, August 8, 2022

    Detour on the Bamfield Main Road starts Monday, August 8, 2022

    Bamfield-Main-Aug-8-Detour
    Starting on Monday, August 8, 2022 the Bamfield Main Road will be closed from 49 – 63 KM. The detour is marked in blue in the map above.
    Please drive with caution and expect delays and other detours.
  • Bamfield Main Road Surfacing Project is in the tender process and will begin soon

    Bamfield Main Road Surfacing Project is in the tender process and will begin soon

    Picture1
    Prepared stockpile area at KM 52

    On February 18, 2022, Huu-ay-aht First Nations announced that construction will begin in late March on the Bamfield Main Road Surfacing Project (BMRSP). It is currently in the tender process and on track for completion by the fall.

    This next phase follows a year of preparation work and finalizing contracts. It includes ditch and culvert repairs and cleaning, placement, and compacting of 250,000 cubic metres of gravel, new roadside barriers, and new signage.

    It was in September 2020 that the Province of B.C. announced they would partner with Huu-ay-aht to bring these upgrades to reality. Fast forward a year and a half, and the road improvements are finally happening.

    “Over the years, too many lives have been lost travelling the road from Port Alberni to Anacla and Bamfield,” said Chief Robert Dennis. “We are pleased that Premier John Horgan took the time to drive the road in 2019 to see first hand how the poor conditions of the road were not only dangerous but an impediment to the economic and social health of our community. His decision to support the road improvements is a turning point for our community. A safer road will enable our tourism plans and make it easier for our citizens to return home.”

    “Our number one focus is helping avoid another heartbreaking tragedy and bringing peace of mind to everyone who travels on Bamfield Road,” said Premier John Horgan. “I want to thank Chief Dennis and the Huu-ay-aht First Nations for their leadership as we work together to support reconciliation goals, create new economic opportunities, and most importantly, keep people safe. Partnerships like these help build a stronger B.C. for everyone.”

    The completed tasks leading up to the tender include:
    • Field Survey of the entire road corridor
    • Design for the road, drainage, barriers, signing, seal coat, and pavement
    • Geotechnical Investigation and Reporting
    • Environmental Overview Report
    • Construction Environmental Management Plan Framework
    • Western Toad and Red-Legged Frog underpass design
    • Concrete box underpasses are being constructed by the end of March
    • Permits for gravel pits from the BC Government
    • Three gravel pits have been investigated. Testing and pit design has been completed. One gravel pit is in full production, one is being cleared, and one is awaiting a final mining permit
    • Six stockpile locations are being constructed. Two stockpile sites are ready with the others under development.
    • Three gravel crushing contracts have been awarded and production at the Rayner Bracht pit and Dolman’s pit near km 0 is underway. Blenheim Pit crushing will begin shortly.

    Construction of the road will progress into July 2022, and this is when the seal coat will begin. The entire 76 KM length of road will be seal coated and be completed by the end of September 2022.

    For more information, contact: Amanda-Lee Cunningham Communications Manager, Huu-ay-aht First Nations 250-723-0100 ext. 256 | amanda.c@acunningham

    View announcement: here

  • Huu-ay-aht and Province mark the beginning of a new path together with Bamfield Main Road Surfacing Project groundbreaking

    Six gold shovels broke the ground today in the territory of Huu-ay-aht First Nations marking the beginning of the physical work for the Bamfield Main Road Surfacing Project.

    The project will include significant safety improvements and chipsealing of the 76-kilometre vital link between Bamfield and Port Alberni. It was announced in Victoria in September 2020 and outlined a partnership between the Province of British Columbia, contributing $25.7 million, and Huu-ay-aht First Nations, covering the remaining $5 million.

    “Today is an exciting day for our Nation – one we have been working towards for decades,” explained Huu-ay-aht Chief Councillor Robert J. Dennis Sr. “We are standing today in an area where our people have lived for centuries, along the Sarita River. It is an important day because we are finally able to use the resources in the best way for our people. When we can say that is always happening, we will have reached true reconciliation.”

    He acknowledged Premier John Horgan and the Provincial government for their commitment to this project. He also noted how helpful MP Gord Johns and former MLA Scott Fraser were in making today a reality, as well as the constant support from MLA Josie Osborne and Alberni-Clayoquot Regional District Director Bob Beckett. Each were present at the event with the exception of the Premier and Fraser, who sent their regrets.

    “The only way to achieve the change we want to see for our Nation is through creating an action plan,” he said. “That is what the Premier did when he travelled to our community almost two years ago. Because of that, we are partnering in a project that will create a safe, reliable road for travellers.”

    Huu-ay-aht First Nations is making history in British Columbia as the first Indigenous community to lead a road infrastructure project of this size.

    “Public safety is at the heart of community well-being,” said Murray Rankin, Minister of Indigenous Relations and Reconciliation. “We partnered with Huu-ay-aht First Nations to invest in upgrades to critical infrastructure in the area, and I applaud the Huu-ay-aht leadership for their steadfast determination to work towards vital road improvements in their territory that will benefit their community and visitors for years to come.”

    The groundbreaking took place at the gravel pit that Huu-ay-aht is developing for the project through HGB Gravel LP. This is the first physical work to take place in the project. When completed, Blenheim Pit will supply the gravel needed for the surfacing of the road. The pit is in Huu-ay-aht’s traditional territory, approximately 30 minutes from its village of Anacla, close to Bamfield on the West Coast of Vancouver Island.

    Other strong supporters of the project were also in attendance, including Tseshaht Chief Councillor Waamiiš (Ken Watts), Shannon Janzen from Western Forest Products, and Domenico Lannidinardo from Mosaic. They all spoke of the importance of working together and that this is how true reconciliation can be accomplished.

    “It is exciting to see this project moving forward. In 2011 when we signed the Maa-nulth Treaty, we knew it would not work unless we work together as a tribe and build partnerships with others. The partnership we have with the province is an example of true reconciliation,” explained Tayii Ḥaw̓ił ƛiišin (Head Hereditary Chief Derek Peters). “We have lost too many lives on this essential link to our community. As a nation, we must continue to move forward together with our Ancient Spirit and Modern Minds. Most importantly, we must do it right and honour our sacred principles of ʔiisaak (utmost respect), ʔuuʔałuk (taking Care of), and Hišuk ma c̕awak (everything is one) and the teachings of our ancestors.”

    The Bamfield Main Road Surfacing Project is a partnership between Huu-ay-aht First Nations ($5 million) and the Province of British Columbia ($25.7 million).

    “The work today at the Blenheim gravel pit is the first step into a better and safer future in the wake of 2019 tragedy,” said Josie Osborne, Minister of Municipal Affairs and MLA for Mid Island-Pacific Rim. “A sincere thank you to Huu-ay-aht First Nations for allowing me to witness this initial important work and I look forward to walking side by side with their community as we build a strong recovery from COVID-19.” 

    Work on the Bamfield Main Road Surfacing Project began earlier this spring when crews carried out a field survey of the 76-kilometre road, culverts, bridges, legal property boundaries, waterline at Fredrick Lake, water courses, and related infrastructure completed. This data is utilized for 3D modeling by the road and drainage design team. An environmental study and road drainage and design has also been completed.

    The geotechnical investigation has also been carried. All the data has been processed and the geotechnical team is finalizing the design requirements to achieve the best roadbed construction for the seal coat application to ensure the roadbed is strong, as this determines how long the seal coat will last.

    Work began in October of 2020 by HGB Gravel LP to identify potential gravel sources along the route. Since then, numerous pits have been identified and investigated for their potential. Currently numerous pits are gaining permits for further investigation. The Blenheim Pit is first of the pits to be developed. The gravel production will carry on through the winter to ensure the required quantities for the road are available for the contracts.

    The road will be constructed in three contract sections of approximately 25 kilometers each. The contracts will be tendered in January 2022 with work to begin in April 2022 and completed by mid-September. These contracts will carry out the gravel placement, compaction, drainage requirements, and signage. The construction will also raise the road in numerous locations to avoid future flooding issues. New concrete box culverts are to be placed near Fredrick Lake to allow the Western Toad population free movement across the road.

    One seal coat contract covering the complete 76.6 km will be tendered in March 2022. The seal coating is expected to be completed by the end of September that allows for weather and other delays. This contract will apply two layers of seal coat and place required barriers. In March 2023, a paving contract will be tendered, this contract will pave the required sections over the previously laid seal coat. The pavement is to be placed on all steep hills, major intersections, and bridge approaches. Along with the pavement, additional barrier sections will be placed to increase the safety in specific locations.